Skip to main content

Live Oak Park Road Bridge Project

Live Oak Park Road and Gum Tree Lane

Rainbow Water partnered with the County of San Diego Department of Public Works on the Live Oak Park Road Bridge Project, to replace the bridge culvert structure with a single-span concrete slab bridge. The new County bridge raised the road elevation three to four feet and removed the existing corrugated metal pipe
culverts currently under the roadway. The County’s bridge project created utility conflicts with the District’s existing 8-inch and 16-inch water mains, that resulted in the need to relocate sections of both mains, which was
the District's responsibility on the Project. The bridge upgrade restores natural flow of water to the area and improves safe road access. 

Start Date: June 8, 2022 (NTP Issued)     End Date:  April 2024

Join our mailing list